Butterfly Project
The Butterfly Project started following the generous donations given to the school in memory of Mrs Mitchell. The school, family and Friends committee met regularly to discuss projects which would be a lasting legacy to her and the exceptional contribution she made to the school and whole community. From this the Butterfly Project commenced.
Fundraising and project updates
Butterfly Project February 2025 update
Butterfly Project June 2024 update
Butterfly Project May 2024 update
Building update
Andy from the All Aspex Group led the tendering stage in September and October 2024 and also submitted the successful planning application before the 2024 summer holidays. We would like to thank Andy for all the work he has done for the Butterfly project.
The Friends of Coulsdon CofE School engaged Marquis Construction Limited to build the Butterfly Room and work commenced in the week of 11 November 2024.
Completion and fit out
In the first half of the spring term 2025 the Butterfly Room had furniture purchased and over half term the remaining items were fitted including an interactive whiteboard. The room was ready for use after half term.
In addition the new sensory room built within the school was completed on 18 March 2025.
Week 5
This week the Butterfly Room was completed inside and outside ready for furniture and equipment to be purchased.
Week 3 & 4
The main part of the external building structure was finished and windows and doors installed. Work started on the internal part of the building. In addition, work has been completed in the Noah's and Rainbow room. The Noah's room has been split into two rooms to allow a sensory room to be installed in early 2025 and the Rainbow room has been redecorated.
Week 2
The main part of the external building structure was built this week.
Week 1
Ground works took place this week and involved the digging out the ground to allow the foundations to be laid.